CRC Staff provide administration of construction projects.

CRC Aministered Projects

Buckingham County VDOT Enhancement Project (Phase I)

Total Budget $276,555

The project includes construction of sidewalks, period street lighting, signage, and landscaping within the Buckingham County Courthouse Village.

Town of Dillwyn VDOT Enhancement Project (Phase IV)

Total Budget – $151,250

The project includes decorative street lighting, new and replacement sidewalks, and trees in Downtown area.

Dillwyn VCDBG Business District Revitalization Project

Total Budget – $1,268,257

The project includes storefront (facade) improvements, a business loan pool, and marketing/branding activities.

Town of Drakes Branch Southern Rivers Wastewater System Improvements Project

Total Budget – $502,538

Installation of emergency pump connections at three pump stations; purchase of a portable trail mounted generator and sewage pump; replacement of various manholes; replacement of existing sewer line; and purchase of sewer inspection equipment.

Town of Victoria VDOT Enhancement Streetscape Project (Phase IA)

Total Budget –$733,750

This project includes the following construction activities within a two-block area along Main Street in downtown Victoria: sidewalks, crosswalks, curb and gutter upgrades, landscaping, benches and traffic calming measures.

Town of Victoria Safe Routes to School Project

Total Budget – $107,000

This project includes physical improvements in the vicinity of Victoria Elementary School including new and improved sidewalks, curbing, new and improved crosswalks and signage.

Prince Edward County EECBG Project – STEPS Manufacturing Facility (Amended)

Total Budget – $350,000

This project received additional funding to repair/replace approximately 14,500 square feet of roof on the STEPS Manufacturing Facility.